To facilitate the construction of the ground floor slab, the Contractor engaged a ready-mix concrete supplier to provide the concrete and a concrete pump truck to place the concrete within the prepared area.
Before concrete is placed for a ground-floor slab, several basic checks should be undertaken to confirm that the prepared work is suitable for the pour. These include, as applicable, verification of the substrate, reinforcement size, spacing and cover, and the adequacy and stability of the formwork.
As an observer, one of the first issues that raised concern was the reinforcement appearing to be resting directly on the substrate. This raises the question of how the required minimum concrete cover is being achieved. For a ground-supported reinforced concrete slab, the specified cover is important not only for durability and protection of the reinforcement from environmental exposure, but also for maintaining the intended position of the reinforcement within the concrete. Where reinforcement is placed directly on the substrate, there is a significant risk that the required cover will not be achieved.
There was also an apparent concern with the formwork. A section of plywood used as formwork did not appear to have any visible stakes or other independent means of support. The fact that it remained upright suggested that it may have been held in position by binding wire attached to the reinforcement. This raises questions about whether the formwork had been adequately secured to resist the pressure exerted during placement and consolidation of the concrete.
At some point, someone had determined that the substrate, reinforcement, and formwork were sufficiently prepared for the concrete pour to proceed. This decision was significant because the concrete pump truck and multiple ready-mix trucks had already arrived on site, indicating that substantial resources had been committed to proceeding with the pour.
Traffic and Public Safety
The restricted space available on the site created an additional safety and traffic-management concern. Approximately 90% of the concrete pump truck was positioned within the site, while the remaining portion occupied the sidewalk. Ready-mix trucks delivering concrete to the pump truck hopper were required to park along the sidewalk and partially within the roadway.This arrangement prevented members of the public from using the sidewalk and reduced the available roadway width. At times, the remaining roadway appeared to be approximately one and a half lanes wide, with only two small vehicles able to pass simultaneously. This raised several questions:
- Who was responsible for monitoring and managing traffic during the concrete pour?
- Who is responsible to ensure arrangements were made to protect pedestrians who were displaced from the sidewalk?
- Why was the area occupied by the concrete trucks and pump truck not properly delineated using cones, barriers, or other appropriate traffic-control devices?
- Was there a designated person responsible for coordinating the movement of delivery trucks and maintaining a safe passage for the public
My interest in observing the concrete pour resulted in me entering the roadway and walking between the parked ready-mix truck and the on-coming traffic. While passing the ready-mix truck, I observed one of the workers standing on the truck but did not realise they were adding water to the concrete mixture. Water splashed from the operation onto me, soiling my shirt with cement paste. Although no injury occurred, the situation could have resulted in a more serious incident. This experience illustrates why a safety programme for a construction site must consider not only the workers but also members of the public who may be affected by the Contractor’s activities. Where construction activities encroach on a sidewalk or roadway, appropriate measures should be implemented to protect pedestrians, motorists, workers, and other road users.
Worker Safety
There were also several observations relating to worker safety. The operator of the concrete pump truck was observed wearing open-toe slippers while operating and moving around the equipment. He was also observed walking on the pump truck’s swing-out, telescoping, and extend-down outriggers. Although no incident occurred, this activity presented several potential hazards. The operator could have:
- injured his feet or toes;
- fallen from approximately 1.5 m (5 ft) above ground level;
- come into contact with an electrical hazard, depending on the proximity of overhead or other electrical services.
The pump truck also appeared to be operating without a remote control. As a result, the operator had to leave the onboard controls and position himself so that he could maintain line of sight with the worker directing the concrete hose. This arrangement creates a potential emergency-response concern. If the operator is away from the controls when an emergency occurs, there may be a delay in stopping the pump or adjusting the boom. The delay in adjusting the boom also appeared to place unnecessary physical strain on the worker handling the delivery hose. The worker was required to push, bend, and redirect a 150 mm diameter rubber hose when adjustments to the boom were delayed. Repeatedly handling and redirecting a hose of this size and weight can expose the worker to significant physical strain, particularly to the back and core muscles.
Concrete Quality
A separate concern relates to the addition of water to the concrete after delivery to the site. Water should not be added to ready-mix concrete at the site simply to increase its flowability unless this is specifically permitted under the approved concrete mix and controlled in accordance with the applicable specification and quality-control procedures.
Uncontrolled addition of water can alter the water-cement ratio and potentially reduce the strength and durability of the finished concrete. Where increased workability is required, an approved admixture should be used in accordance with the approved mix design and the manufacturer’s and specification requirements. Any adjustment to the concrete mix on site should be properly controlled and documented.
Duration and Scale of the Pour
The concrete pour lasted more than eight hours and involved the delivery and placement of approximately 230 m³ of concrete which is approximately 31 truckloads and took more than 8 hours. The scale and duration of the operation demonstrate why adequate preparation, supervision, traffic management, worker protection, and quality control should have been established before the first truck arrived on site.
A concrete pour of this magnitude is not simply a matter of delivering concrete and placing it. It requires coordination of the prepared substrate, reinforcement, formwork, concrete supply, testing, placement, equipment, workers, traffic, pedestrians, and emergency arrangements. The observations made during this pour raise questions about whether these elements were adequately planned, checked, and supervised before and during the operation.